Application for electrical supply
1. Each application shall be submitted by Corenet and consist of the following documents:
| i) |
Application Form EME2621
|
![]() |
| ii) |
A copy of CS/5 or
|
![]() |
|
a copy of CS/7 (exceeding 45 KVA)
|
![]() |
|
| iii) |
A copy of endorsed single line diagram
|
|
| iv) |
Authorisation for partnerships or
|
![]() |
|
Resolution for Pte Ltd
|
![]() |
All Forms and single line diagram to be scanned in “pdf” format.
2. All entries in the CS/5 or CS/7 shall tally with the application form.
3. For application for increase in electrical loading above the approved load, the approval is subject to the availability of electricity supply in the building. The standard charges per additional ampere are as follows:
- $45* for rental premises
- $85* for sold premises
- $200* administrative charge
(*cost is before GST)
4. The Licensed Electrical Worker (LEW) engaged by the Registered Tenant/Lessee is fully responsible for any electrical installations at the premises and ensure that any additional rewiring does not exceed the approved electricity load.
5. No work to be carried out prior HDB / Energy Market Authority (EMA)'s approval.
6. The Registered Tenant/ Lessee is to ensure that structural members are not affected during the course of electrical work.